Development tracker

Commercial development in San Francisco, CA: projects by status, checked October 2026

SF Planning calls Mission Rock "an approved, mixed-use development at Seawall Lot 337 and Pier 48". † The Office of Community Investment and Infrastructure says of Candlestick Point and the Hunters Point Shipyard Phase 2 area: "While most of the project is in the pre-development phase". † † This tracker lists each project with its status and date exactly as its source states them, so you can see what is approved, what is built and what is still in review.

Last updated October 28, 2026

How to read this tracker

Each line quotes or closely follows one public source: a Port of San Francisco report or page, an SF Planning page, an Office of Community Investment and Infrastructure page, a Transbay Joint Powers Authority report, or a dated news article. Projects sit under the name their source page or article uses. Where a quote does not name the project, the line names its source instead, and two records are joined only when one quote ties them.

A status is a snapshot from the day its source was written. Before you price a nearby building or a site on the strength of a project, call the agency that owns the file and ask what has changed since.

Approved projects in San Francisco

Mission Rock

  • SF Planning describes Mission Rock as "an approved, mixed-use development at Seawall Lot 337 and Pier 48, an approximately 28-acre Port-owned property across McCovey Cove from Oracle Park." †
  • The San Francisco Chronicle reported on June 6, 2024 that "the payments giant has moved about 1,000 workers into the white, 300,000-square-foot building at Dr. Maya Angelou Lane and Toni Stone Crossing". † The Chronicle added that "Visa’s building and the larger Mission Rock project are co-owned by the baseball team and developer Tishman Speyer". †

SF Planning project with 1.8 million gross square feet of commercial uses

  • SF Planning's project page lists approximately 1.8 million gross square feet of commercial uses, including 100,000 square feet of retail, 800,000 square feet of office and 650,000 square feet of life science or laboratory space. †
  • The same SF Planning page states that its listed approvals "were unanimously approved by the Planning Commission and Board of Supervisors in January 2020 and April 2020, respectively". †
  • The page also lists "Design Review Approval Block 2 (February 3, 2026)". †

Dogpatch waterfront apartment financing

  • The San Francisco Standard reported on August 3, 2026 on a lender "committing nearly $200 million in financing for a 342-unit apartment project on the Dogpatch waterfront". † The Standard also reported: "The commissioners approved unanimously, sending the decision to the Board of Supervisors." † The quoted words name neither the SF Planning project above nor the item the commissioners voted on, so this tracker lists the article on its own. Read it before you rely on it.

Candlestick Point and Hunters Point Shipyard Phase 2

  • The Office of Community Investment and Infrastructure states that the project "is a 693-acre, master-planned, urban infill project approved for implementation along the southeastern edge of San Francisco". †
  • The same office states: "While most of the project is in the pre-development phase". †
Office and R&D space in the program table, as the Office of Community Investment and Infrastructure prints it †
Candlestick PointHPS Phase 2Total
Office and R&D Space2,800,000 square feet2,096,500 square feet4,896,500 square feet

570 Market St. hotel

  • The San Francisco Examiner reported on September 12, 2025: "The commission on Thursday approved the building of a 211-room hotel at 570 Market St." †
  • The Examiner described the plan as a 29-story, roughly 300-foot-tall boutique hotel tower in the heart of the Financial District. †

536 Mission St.

  • The San Francisco Standard reported in September 2026 that two firms "paid roughly $31.6 million for the former Golden Gate University campus at 536 Mission St." †
  • In the same article, The Standard reported: "This week, city planners approved two versions of the project: a fully commercial, 1.35-million-square-foot office tower". †
  • Our October 2026 research did not find a quote that ties that vote to the purchase above, so this tracker keeps them as two separate entries.

When a sale and an approval appear in the same story, ask the city for the file that names the parcel before you treat them as one project.

SF Gateway in Bayview: the approved multi-story PDR project

Lee & Associates calls this Bayview warehouse project "Prologis’s SF Gateway" and places it "in the Bayview". † This tracker sets out the size each source gives, with its date. The Real Deal reported in June 2025 that "It would be on a 17-acre site owned by Prologis at 749 Toland Street in Bayview". † SF Standard reported in September 2025 that the project "received approval from the Planning Commission" for "17 acres bounded by Kirkwood Avenue, Rankin Street, McKinnon Avenue, and Toland Street". †

How big is it? Three sources, three figures

  • The San Francisco Planning Department's Notice of Determination, filed December 17, 2025: "The two three-story buildings would total approximately 1,646,000 gross square feet of enclosed floor area, or 2,160,000 gross square feet including active roofs." †
  • The Real Deal, June 4, 2025: "two, three-story buildings totaling more than 2 million square feet". †
  • Lee & Associates, Q4 2025 industrial report: "approved Prologis’s SF Gateway, a planned 1.6 million square foot warehouse project in the Bayview". †

The figures measure different things at different dates: enclosed floor area, area with usable roofs, and a rounded headline. None of them is wrong on its own terms. Quote the one that matches your question, with its source, and never mix them.

What the Planning notice records

The notice quoted here is the Planning Department document filed for the San Francisco Gateway Project; its title and link are in the Sources list. The notice says "The project site is currently occupied by four single-story structures totaling approximately 448,000 square feet of production, distribution, and repair (PDR) space", and that the project would "construct two new multi-story PDR buildings". † It lists Case 2015-012491ENV, the "Production, Distribution, and Repair 2" district and the "65-J Height and Bulk District". †

According to the notice, "Approximately 1,125 parking spaces for standard automobiles would be provided" and "each building would include 36 loading dock doors at level 1". † On approvals, it states: "The project was officially approved on October 28, 2025 when no appeal of the FEIR was filed." † It adds that "The City and County of San Francisco decided to carry out or approve the project on December 12, 2025". †

Who the buildings are for, and the retail exemption

SF Standard reported that the buildings "could be used by a variety of production, distribution, and repair (known as PDR) businesses and would not be built with particular tenants in mind". † The same article describes the site's zoning as rules "which allow for industrial use only" and reports that "Prologis needs this exemption in order to construct 8,400 square feet of ground-floor retail space." †

If you own industrial property nearby, a large new multi-story building changes what tenants compare your space against once it delivers. Watch the building permit file for the case, not only the headlines, before you set rents or a sale price on the strength of it.

Built, occupied or restarted in San Francisco, as the sources state it

The sources in this section speak of certificates, completion notices, occupancy and a restart, not of active construction, so each line keeps the source's own words.

Port of San Francisco project page: parks, homes and an arts facility

  • The Port of San Francisco's project page lists 6.5 acres of waterfront and upland parks and 1,100 to 2,150 residential units. †
  • The Port of San Francisco page also lists a "90,000 sq. ft. arts facility & replacement studio space for Noonan Building artists". †

The Port of San Francisco annual report, fiscal year ended in June 2024

The quoted lines below come from the Port's annual report. The quoted words do not name the project each line belongs to, so each is listed as its own entry; read the report section around it to see which waterfront project it covers.

  • The Port of San Francisco's annual report for the fiscal year ended in June 2024 states that "Parcel F received its TCO and welcomed its first residents in June 2024." †
  • The same Port of San Francisco report states: "The developer submitted the Phase 2 project application to the Port in December 2022". †
  • The report also states: "Public Works issued a Notice of Completion (NOC) for Phase 1 infrastructure, aside from parks, in November 2022." †
  • It describes the "rehabilitation of historic Building 12, which has a final certificate of occupancy and has begun leasing". †

Oceanwide Center

  • The San Francisco Standard reported in September 2026: "The previously abandoned Oceanwide Center development started back up this year." †

An occupancy certificate on one building does not mean the rest of a district is built. Read the phase that sits next to your parcel.

Proposed and in review in San Francisco

Bayview industrial site, Kirkwood Avenue to Toland Street

  • The San Francisco Standard reported in September 2025 on a plan "demolishing four industrial buildings spread across 17 acres bounded by Kirkwood Avenue, Rankin Street, McKinnon Avenue, and Toland Street". †
  • The Standard described "two structures totaling more than 1.6 million square feet". †
  • The Standard reported that "the Planning Commission voted unanimously to certify the project’s environmental impact report". † It added: "The firm can break ground once the Board of Supervisors approves the final plan." †

530 Sansome St., Jackson Square

  • The San Francisco Standard reported in June 2025: "Related proposes the construction of two buildings on a block bound by Sansome, Washington, Battery, and Merchant streets." †
  • The same article states: "One component is a 41-story mixed-use building with 375,000 square feet of office space atop a 200,000-square-foot hotel." †
  • In September 2026, The Standard reported: "McCourt is also partnering with Related Companies to co-develop a 41-story mixed-use tower at 530 Sansome St. in Jackson Square." †

900 7th St.

  • The San Francisco Standard reported in September 2026: "Amazon in February was able to push its proposed delivery warehouse at 900 7th St. into the environmental review stage". †

Environmental review and a commission vote come before permits and financing. If you own next to a project in review, follow the hearing calendar and read the environmental document, because a design can change before it is built.

Infrastructure in San Francisco: The Portal and the Embarcadero Seawall

The Portal

  • The Transbay Joint Powers Authority's December 2025 report gives "an indicative total project cost of $7.572 billion, as presented to the TJPA Board in July 2025". †
  • The report states: "The release of the 40-CT RFP is scheduled for mid-December, which will lead to the award of the 40-CT contract in the fourth quarter of 2026." †
  • It also states: "The 10-UR contract for utility relocation along Townsend Street is identified as a priority". †
  • On funding, the report states: "Obtaining an FFGA is the final step in securing the federal share of The Portal’s funding." †

The Embarcadero Seawall

  • The Port of San Francisco states: "The Port is leading the Embarcadero Seawall Program, a citywide effort to create a more sustainable and resilient waterfront." †
  • The Port of San Francisco's resilience page refers to "7.5 miles of waterfront within the Port of San Francisco's jurisdiction, from Aquatic Park to Heron's Head Park". †
  • The Port of San Francisco reports: "In August 2026, the Flood Study was finalized with the release of a Recommended Plan". † Its program page lists a "Draft Plan, released for public review in 2024". †

If you own along the waterfront or near the rail alignment, read the agency's latest plan and contract schedule yourself. Infrastructure dates move, and the dates in this section are the ones each source printed.

City plans: the General Plan, area plans and housing element in San Francisco

SF Planning states that "San Francisco's first General Plan was adopted by the Planning Commission in 1945". † Its Downtown Plan text states: "The Downtown Plan contains a Sub-Area plan for the area located around the Transbay Transit Center." † It adds: "The Transit Center District Sub-Area Plan builds on the Downtown Plan to envision this area as the heart of a growing downtown." †

On housing, SF Planning states that "The Housing Element 2022 Update was adopted in January 2023" and that the plan runs "January 31, 2023 to January 31, 2031". † SF Planning states that HCD found the Housing Element in full compliance on January 20, 2023. † It gives the city's allocation: "San Francisco's RHNA allocation for the 2023-2030 cycle is 82,069 housing units". †

SF Planning states: "On December 12, 2025, following more than three years of community engagement, plan development, and approvals by both the Planning Commission and the Board of Supervisors, Mayor Lurie officially signed the Family Zoning Plan into law." †

The Office of Resilience and Capital Planning states that the city's Capital Plan "was approved by the Board of Supervisors on April 15, 2025" and that "This Capital Plan was amended in December 2025 to update the General Obligation bond schedule." † †

In the southeast, the Office of Community Investment and Infrastructure states: "Outside of Candlestick Point, the Bayview Hunters Point Redevelopment Project Area is inactive since the dissolution of California redevelopment law in 2011." † It states that "In June 2010, the redevelopment plans for Bayview Hunters Point and the Hunters Point Shipyard were amended to facilitate the integrated development of the Candlestick Point area and the Hunters Point Shipyard Phase 2 area under one developer and as one development project known as CP-HPS Phase 2." †

Plans set what can be built; projects are what someone chose to build. Read the plan that covers your parcel before you read the projects around it.

Development questions owners ask about San Francisco

Is Oceanwide Center still being built?

The latest source in this tracker says it restarted. The San Francisco Standard reported in September 2026 that "The previously abandoned Oceanwide Center development started back up this year." Check the permit file for the parcel before you treat that as a construction schedule. †

What is The Portal downtown rail extension?

It is a Transbay Joint Powers Authority project. The authority's December 2025 report gives "an indicative total project cost of $7.572 billion, as presented to the TJPA Board in July 2025" and states that "Obtaining an FFGA is the final step in securing the federal share of The Portal’s funding." A cost figure like that is an estimate, so read the latest board report before you plan around it. ††

What is Mission Rock?

SF Planning describes Mission Rock as "an approved, mixed-use development at Seawall Lot 337 and Pier 48, an approximately 28-acre Port-owned property across McCovey Cove from Oracle Park." Its later phases depend on separate applications, so read each phase on its own. †

How much office space is planned at Candlestick Point and Hunters Point Shipyard?

The Office of Community Investment and Infrastructure program table lists "Office and R&D Space 2,800,000 square feet 2,096,500 square feet 4,896,500 square feet" under the columns Candlestick Point, HPS Phase 2 and Total. It also states: "While most of the project is in the pre-development phase". A program figure is a ceiling in a plan, not a building under way. ††

Was the hotel at 570 Market St. approved?

Yes. The San Francisco Examiner reported on September 12, 2025 that "The commission on Thursday approved the building of a 211-room hotel at 570 Market St." A commission vote is one step; permits still follow. †

How many housing units is San Francisco planning for in 2023 to 2030?

SF Planning states that "San Francisco's RHNA allocation for the 2023-2030 cycle is 82,069 housing units divided into very low, low, moderate, and above moderate income categories." That allocation is a state target, not a count of buildings. †

What is the big warehouse project planned in Bayview?

It is Prologis' SF Gateway. Lee & Associates' Q4 2025 industrial report describes "Prologis’s SF Gateway, a planned 1.6 million square foot warehouse project in the Bayview", and reports it as approved. The Planning Department's notice gives a different size, "approximately 1,646,000 gross square feet of enclosed floor area, or 2,160,000 gross square feet including active roofs", so name the source whenever you quote a size. ††

Next step

The zoning guide sets out the review steps and timelines these projects pass through.

Read the zoning and permits guide

Sources

  1. SF Planning Department. sfplanning.org/project/mission-rock
  2. Port of San Francisco, Fiscal year ended June 30, 2024. sfport.com/media/10313/download?inline=
  3. Port of San Francisco, Fiscal year ended June 30, 2024. sfport.com/media/10313/download?inline=
  4. San Francisco Chronicle, 2024-06-06. www.sfchronicle.com/sf/article/visa-new-office-19484682.php
  5. San Francisco Chronicle, 2024-06-06. www.sfchronicle.com/sf/article/visa-new-office-19484682.php
  6. SF Planning Department. sfplanning.org/potrero-power-station
  7. SF Planning Department. sfplanning.org/potrero-power-station
  8. SF Planning Department. sfplanning.org/potrero-power-station
  9. The San Francisco Standard, 2026-08-03. sfstandard.com/2026/08/03/jpm-sf-housing-potrero-power-station/
  10. The San Francisco Standard, 2026-08-03. sfstandard.com/2026/08/03/jpm-sf-housing-potrero-power-station/
  11. Office of Community Investment and Infrastructure. sfocii.org/projects/hunters-point-shipyard-candlestick-point-2/overvie
  12. Office of Community Investment and Infrastructure. sfocii.org/projects/hunters-point-shipyard-candlestick-point-2/overvie
  13. Office of Community Investment and Infrastructure. sfocii.org/projects/hunters-point-shipyard-candlestick-point-2/overvie
  14. San Francisco Examiner, 2025-09-12. www.sfexaminer.com/news/business/new-downtown-sf-hotel-tower-approved-
  15. San Francisco Examiner, 2025-09-12. www.sfexaminer.com/news/business/new-downtown-sf-hotel-tower-approved-
  16. The San Francisco Standard, 2026-09-24. sfstandard.com/2026/09/24/office-boom-san-francisco-housing-shortage/
  17. The San Francisco Standard, 2026-09-24. sfstandard.com/2026/09/24/office-boom-san-francisco-housing-shortage/
  18. Port of San Francisco. www.sfport.com/projects-programs/pier-70-28-acre-site
  19. Port of San Francisco. www.sfport.com/projects-programs/pier-70-28-acre-site
  20. Port of San Francisco, Fiscal year ended June 30, 2024. sfport.com/media/10313/download?inline=
  21. Port of San Francisco, Fiscal year ended June 30, 2024. sfport.com/media/10313/download?inline=
  22. The San Francisco Standard, 2026-09-24. sfstandard.com/2026/09/24/office-boom-san-francisco-housing-shortage/
  23. The San Francisco Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  24. The San Francisco Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  25. The San Francisco Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  26. The San Francisco Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  27. The San Francisco Standard, 2025-06-25. sfstandard.com/2025/06/25/related-california-office-development-jackso
  28. The San Francisco Standard, 2025-06-25. sfstandard.com/2025/06/25/related-california-office-development-jackso
  29. The San Francisco Standard, 2026-09-24. sfstandard.com/2026/09/24/office-boom-san-francisco-housing-shortage/
  30. The San Francisco Standard, 2026-09-24. sfstandard.com/2026/09/24/office-boom-san-francisco-housing-shortage/
  31. Transbay Joint Powers Authority, 2025-12-11. tjpa.org/media/40259/download?inline=
  32. Transbay Joint Powers Authority, 2025-12-11. tjpa.org/media/40259/download?inline=
  33. Transbay Joint Powers Authority, 2025-12-11. tjpa.org/media/40259/download?inline=
  34. Transbay Joint Powers Authority, 2025-12-11. tjpa.org/media/40259/download?inline=
  35. Port of San Francisco, 2026-08. www.sfport.com/wrp/embarcadero-seawall-resilience
  36. Port of San Francisco. www.sfport.com/wrp/embarcadero-seawall-resilience
  37. Port of San Francisco. www.sfport.com/wrp/embarcadero-seawall-resilience
  38. Port of San Francisco. www.sfport.com/wrp
  39. SF Planning Department. generalplan.sfplanning.org/
  40. SF Planning Department. generalplan.sfplanning.org/Downtown.htm
  41. SF Planning Department. generalplan.sfplanning.org/Downtown.htm
  42. SF Planning Department. sfplanning.org/project/housing-element-update-2022
  43. SF Planning Department. sfplanning.org/project/housing-element-update-2022
  44. SF Planning Department. sfplanning.org/project/housing-element-update-2022
  45. SF Planning Department. sfplanning.org/sf-family-zoning-plan
  46. Office of Resilience and Capital Planning, SF.gov. www.sf.gov/10-year-capital-plan
  47. Office of Resilience and Capital Planning, SF.gov. www.sf.gov/10-year-capital-plan
  48. Office of Community Investment and Infrastructure. sfocii.org/projects/hunters-point-shipyard-candlestick-point-2/overvie
  49. Office of Community Investment and Infrastructure. sfocii.org/projects/hunters-point-shipyard-candlestick-point-2/overvie
  50. San Francisco Planning Department, Notice of Determination (filed with County Clerk), 2025-12-17. media.api.sf.gov/documents/2025-0000092_San_Francisco_Gateway_Project.
  51. San Francisco Planning Department, Notice of Determination (filed with County Clerk), 2025-12-17. media.api.sf.gov/documents/2025-0000092_San_Francisco_Gateway_Project.
  52. San Francisco Planning Department, Notice of Determination (filed with County Clerk), 2025-12-17. media.api.sf.gov/documents/2025-0000092_San_Francisco_Gateway_Project.
  53. San Francisco Planning Department, Notice of Determination (filed with County Clerk), 2025-12-17. media.api.sf.gov/documents/2025-0000092_San_Francisco_Gateway_Project.
  54. San Francisco Planning Department, Notice of Determination (filed with County Clerk), 2025-12-17. media.api.sf.gov/documents/2025-0000092_San_Francisco_Gateway_Project.
  55. SF Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  56. SF Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  57. SF Standard, 2025-09-26. sfstandard.com/2025/09/26/prologis-mega-project-bayview-gets-thumbs-ci
  58. The Real Deal, 2025-06-04. therealdeal.com/san-francisco/2025/06/04/prologis-gateway-project-poss
  59. Lee & Associates, Q4 2025. www.lee-associates.com/wp-content/uploads/2026/01/2025-Q4-San-Francisc